List of Figures
List of Tables
The Author
Preface
Acknowledgements
Part I Background and Concepts of the Red Book
Chapter 1 Background of the Red Book
1.1 The ACE Form
1.2 The First Edition of the Red Book
1.3 The Second and Third Editions of the Red Book
1.4 The Fourth Edition of the Red Book
1.5 The 1996 Supplement to the Red Book
1.6 Concepts of the Red Book
1.7 The new suite of FIDIC contracts
Chapter 2 The Red Book is Based on a Domestic Contract
2.1 Introduction
2.2 Diversity of legal systems
2.3 The applicable law in international construction
2.4 The applicable law of the contract
2.5 Law governing procedure
2.6 Law governing enforcement of awards
2.7 Grouping of the contemporary legal systems
2.8 The Romano-Germanic group
2.9 The common law group
2.10 The law in Islamic countries
Chapter 3 Legal Concepts Based on the Common Law System
3.1 The law applicable to the contract
3.2 Conflict
3.3 Some specific concepts under the common law
3.4 Tort
3.5 Contract – general principles
3.6 Privity of contract
3.7 Performance of a contract
3.8 The contents of a contract
3.9 Remedies for breach of contract
3.10 Exclusion clauses
3.11 The responsibility to complete
Chapter 4 Drafting Principles
Chapter 5 The Concept of a Trusted Independent Engineer
5.1 Introduction
5.2 Other suppliers of consulting services
5.3 Services provided by the consulting engineer
5.4 Independence
Chapter 6 A Traditional Re-measurement Contract
6.1 Factors governing choice of contract
6.2 The allocation of essential functions
6.3 Re-measurement contracts
6.4 Cost-reimbursable contracts
6.5 Lump sum contracts
Chapter 7 Sharing of Risks
7.1 Introduction
7.2 The definition of ‘risk’
7.3 Measurement of risk
7.4 Risk management
7.5 Allocation of risks and their management
7.6 Allocation of risks in the Red Book
7.7 Responsibility and liability
7.8 Indemnity and insurance
Chapter 8 The Concepts in Practice
8.1 The Red Book in use
8.2 Areas of conflict
8.3 EIC/FIDIC survey of 1996
8.4 A brief summary of Part I
Part II The Fourth Edition: A Commentary
Chapter 9 The Revisions – Purposes and Consequences
9.1 Introduction
9.2 Clause 1
9.3 Clause 2
9.4 Sub-clause 5.2
9.5 Sub-clauses 6.1, 6.4 and 6.5
9.6 Clause 7
9.7 Clause 8
9.8 Clause 10
9.9 Sub-clause 12.2
9.10 Clause 13
9.11 Sub-clauses 14.1 and 14.3
9.12 Clause 15
9.13 Clause 19
9.14 Clause 20
9.15 Clause 21
9.16 Clause 23
9.17 Clause 25
9.18 Clause 27
9.19 Clause 28
9.20 Clause 30
9.21 Clauses 34 and 35
9.22 Sub-clause 36.5
9.23 Clause 37
9.24 Clause 40
9.25 Clause 41
9.26 Sub-clause 42.3
9.27 Clause 44
9.28 Clause 46
9.29 Clause 51
9.30 Sub-clause 52.3
9.31 Clauses 53 and 54
9.32 Sub-clause 57.2
9.33 Clause 60
9.34 Sub-clauses 65.4 and 66.1
9.35 Clause 67
9.36 Clause 69
9.37 Other changes made in the 1992 Reprint
9.38 Concluding remarks
Part III The Fourth Edition in Practice
Chapter 10 Role of the Engineer
10.1 Introduction
10.2 The engineer as a designer
10.3 The engineer as the employer’s agent
10.4 The engineer’s proactive duties and authority
10.5 The engineer’s reactive duties and authority
10.6 The engineer’s passive duties and authorities
10.7 The engineer as a supervisor
10.8 The engineer as certifier
10.9 The engineer as adjudicator or quasi-arbitrator
10.10 Concluding remarks
Chapter 11 Responsibility and Liability of the Engineer
11.1 Introduction
11.2 Responsibility of the engineer towards the employer
11.3 Responsibility of the engineer towards the contractor
11.4 The responsibility of the engineer towards third parties (other than the contractor)
11.5 The responsibility of the engineer towards society; employees; and the engineer himself
11.6 Liability in construction
11.7 Levels of liability
Chapter 12 The Employer’s Obligations
12.1 Introduction
12.2 Identification of specific elements of the project
12.3 Appointment of engineer
12.4 Possession of site
12.5 To provide instructions as and when they are required
12.6 The employer is to refrain from taking any action which would impede or interfere with the progress of the works
12.7 The employer is to supply materials and carry out works if these form part of the work as defined in the contract
12.8 The employer is to nominate specialist sub-contractors and suppliers as and when they are required
12.9 To permit the contractor to carry out the whole of the works
12.10 To make payments and to make them on time
12.11 Additional obligations for the employer under the Fourth Edition of the Red Book
Chapter 13 The Contractor’s Obligations
13.1 Introduction
13.2 The contractor’s obligations during the tendering stage
13.3 The contractor’s obligations following the letter of acceptance and during the construction stage up to substantial completion
13.4 Contractor’s obligations after substantial completion of the works
Chapter 14 Risks, Liabilities, Indemnities and Insurances
14.1 Introduction
14.2 The Red Book provisions relating to risk, responsibility, liability, indemnity and insurance
14.3 Clause 20 of the Red Book – ‘20.1: care of the works’; ‘20.2: responsibility to rectify loss or damage’; ‘20.3: loss or damage due to employer’s risks’; and ‘20.4: employer’s risks’
14.4 Clause 65 of the Red Book (sub-clauses 65.1 to 65.8) – special risks
14.5 Clause 21 of the Red Book – insurance
14.6 Clause 22 of the Red Book – indemnity for damage to persons and property other than the works
14.7 Clause 23 of the Red Book – third party insurance
14.8 Clause 24 of the Red Book – injury to workmen and insurance
14.9 Clause 25 of the Red Book – general insurance requirements
14.10 Part II of the Red Book – insurance arranged by the employer
14.11 Definitions
Chapter 15 Performance and other Securities
15.1 Introduction
15.2 The spectrum of securities
15.3 Types of securities
15.4 Characteristics of performance bonds and guarantees
15.5 The ICC Uniform Rules for Demand Guarantees
15.6 Uniform Rules for Contract Bonds
15.7 Insurance against unfair calling
15.8 Performance securities under the Red Book
15.9 Examples of securities provided
15.10 Other securities associated with a construction contract
15.11 Concluding remarks
Chapter 16 Claims and Counterclaims
16.1 Introduction
16.2 Definition and legal basis of claims and counterclaims
16.3 A claim under the contract and based on its provisions
16.4 A claim arising out of or in connection with the contract
16.5 Procedure for claims for additional payment – clause 53
16.6 The presentation of claims
16.7 Quantum
16.8 Failure to follow the claims procedure
16.9 Concluding remarks
Chapter 17 Delay in Completion and Claims for Extension of Time
17.1 Time is of fundamental importance
17.2 Clauses 43, 44, 46, 47 and 48 of the Red Book
17.3 Relevant clauses of the Fourth Edition of the Red Book to an extension of time under clause 44
17.4 Programming
17.5 Concurrent delays
17.6 Claims for both extension of time and money
17.7 Liquidated damages
17.8 The Society of Construction Law Delay and Disruption Protocol
Chapter 18 Certificates and Payments
18.1 Introduction
18.2 Interim payment certificates
18.3 Taking-over certificate
18.4 Defects liability certificate
18.5 Final payment certificate
18.6 The engineer is to certify a valuation at date of termination
18.7 Common requirements
18.8 Late certification
Chapter 19 Disputes Settlement by Arbitration
19.1 Introduction and background
19.2 Advantages of arbitration
19.3 What is a dispute?
19.4 What is arbitration?
19.5 The arbitration agreement
19.6 Sources of law in arbitration
19.7 The arbitrator
19.8 The arbitration agreement under clause 67 of the Red Book
19.9 The 1996 supplement to the Fourth Edition of the Red Book
19.10 The ICC Rules of Arbitration
19.11 Why does arbitration in construction disputes continue to lose favour?
19.12 Concluding remarks
Chapter 20 Amicable Settlement Using Alternative Dispute Resolution
20.1 Introduction
20.2 Methods of dispute settlement
20.3 Direct negotiation
20.4 Mediation
20.5 Conciliation
20.6 Mini-trial procedure
20.7 Dispute Board, Dispute Review Board and Dispute Adjudication Board
20.8 Adjudication
20.9 The ICC Rules for Amicable Dispute Resolution
20.10 Pre-arbitral referee procedure
20.11 The ICC Rules for Expertise
20.12 Concluding remarks
Part IV Other Documents Related to the Red Book
Chapter 21 FIDIC’s Other Forms of Contract (1993–1999)
21.1 Introduction
21.2 The Yellow Book, third edition
21.3 The Orange Book, first edition
21.4 The conditions of subcontract for works of civil engineering construction
21.5 Other publications of FIDIC
Part V The 1999 Green Book; The 1999 Red Book; The 1999 Yellow Book; The 1999 Silver Book; Dispute Boards
Chapter 22 The 1999 FIDIC Suite of Contracts
22.1 Introduction
22.2 Differences in format
22.3 Differences in concept
22.4 The 1999 Green Book
Chapter 23 The 1999 Red Book
23.1 Introduction
23.2 The 1999 Red Book: concepts and content
23.3 The 1999 Red Book: new concepts
23.4 Some highlights of the 1999 Red Book
Chapter 24 The 1999 Yellow Book
24.1 Introduction
24.2 Tendering under, and using, the 1999 Yellow Book
24.3 The 1999 Yellow Book: The employer’s requirements
Chapter 25 The 1999 Silver Book
25.1 Introduction
25.2 The 1999 Silver Book: the shifted risks
25.3 The 1999 Silver Book: concepts and content
Chapter 26 Dispute Boards
26.1 Introduction
26.2 Main advantages of the Dispute Board
26.3 Background and evolution
26.4 Types of Dispute Boards
26.5 Varieties of Dispute Boards
26.6 Dispute Adjudication Boards under the FIDIC Contracts
26.7 The role of the Dispute Adjudication Board
26.8 Establishment of the Dispute Adjudication Board
26.9 Obligations of the parties and the members of the Dispute Adjudication Board
26.10 Powers of the Dispute Adjudication Board
26.11 Procedures relating to site visits and meetings
26.12 Procedures relating to referral of a matter to the Board for its opinion
26.13 Procedures relating to referral of a dispute to the Board for its decision
26.14 Remuneration of the members of the Dispute Adjudication Board
26.15 Cost of maintaining the members of the Dispute Adjudication Board
26.16 The decision of the Dispute Adjudication Board
Part VI Comparison between text of the three 1999 Major Books: Red, Yellow and Silver Books
Chapter 27 A Precise Record of the Alterations, Omissions and Additions in the 1999 Yellow and Silver Books as compared with the 1999 Red Book
Appendices
A Editorial Amendments in the 1988 Reprint of the Fourth Edition of the Red Book
B Further Amendments in the 1992 Reprint of the Fourth Edition of the Red Book
C Part II – Conditions of Particular Application
References
Table of Cases
Index
In September 1999, FIDIC introduced its new Suite of Contracts, which included a ‘new’ Red, Yellow, Silver and Green forms of contract. The ‘new’ Red Book was intended to replace the 1992 Fourth Edition of the Red Book, with the ambition that its use would cease with time. This ambition has not materialised and is unlikely to do so in the future.
Despite the importance of the 1999 forms, there has been very little published on the new concepts adopted in them and how they interact with the previous forms. This important work considers these aspects together with the many developments affecting the Fourth Edition of the Red Book that have taken place since 1997, when the second edition of this book was published, and relates them to key contracting issues. It is written by a chartered engineer, conciliator and international arbitrator with wide experience in the use of the FIDIC Forms and in the various dispute resolution mechanisms specified in them.
Important features of this book include:
© 2005 Nael G. Bunni
Editorial offices:
Blackwell Publishing Ltd, 9600 Garsington Road, Oxford OX4 2DQ, UK
Tel: +44 (0)1865 776868
Blackwell Publishing Inc., 350 Main Street, Malden, MA 02148–5020, USA
Tel: +1 781 388 8250
Blackwell Publishing Asia Pty Ltd, 550 Swanston Street, Carlton, Victoria 3053, Australia
Tel: +61 (0)3 8359 1011
The right of the Author to be identified as the Author of this Work has been asserted in accordance with the Copyright, Designs and Patents Act 1988.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, except as permitted by the UK Copyright, Designs and Patents Act 1988, without the prior permission of the publisher.
First edition published 1991
Reprinted 1993, 1994, 1996
Second edition published 1997
Reprinted 1998, 2000, 2001, 2004
Third edition published 2005
Library of Congress Cataloging-in-Publication Data
Bunni, Nael G.
The FIDIC forms of contract : the fourth edition of the Red Book, 1992, the 1996 Supplement, the 1999 Red Book, the 1999 Yellow Book, the 1999 Silver Book / Nael G. Bunni.—3rd ed.
p. cm.
Rev. ed. of: The FIDIC form of contract, 2nd ed. 1997.
Includes bibliographical references and index.
ISBN 13: 978-14051-2031-9 (alk. paper)
ISBN 10: 1-4051-2031-2 (alk. paper)
1. Engineering contracts. 2. Standardized terms of contract. I. Bunni, Nael G. FIDIC form of contract. II. International Federation of Consulting Engineers. III. Title.
K891.B8B86 2005
343′.07862—dc22
2005041189
ISBN 10: 1-4051-2031-2
ISBN 13: 978-14051-2031-9
A catalogue record for this title is available from the British Library
The publisher’s policy is to use permanent paper from mills that operate a sustainable forestry policy, and which has been manufactured from pulp processed using acid-free and elementary chlorine-free practices. Furthermore, the publisher ensures that the text paper and cover board used have met acceptable environmental accreditation standards.
For further information on Blackwell Publishing, visit our website:
www.blackwellpublishing.com
Figure 2.1 | Areas of the law affecting construction in the Romano-Germanic group. |
Figure 2.2 | Areas of the law affecting construction in legal systems based on common law. |
Figure 3.1 | Remedies for breach of contract in the common law system. |
Figure 7.1 | Risks in construction under the FIDIC Red Book, Fourth Edition. |
Figure 7.2 | Indemnities and possible insurance covers for a construction project. |
Figure 13.1 | Acceptance of tender and commencement of works. |
Figure 14.1 | Flow of risk into responsibility, liability, indemnity and insurance. |
Figure 14.2 | Indemnities and insurances relating to risks of injury and damage under the Fourth Edition of the FIDIC Red Book. |
Figure 14.3 | Indemnity and insurance relating to financial risks, etc. |
Figure 14.4 | Consequences of risks eventuating. |
Figure 14.5 | The insurance scheme as in the Fourth Edition of the Red Book. |
Figure 15.1 | The two alternatives of issuing a performance guarantee. |
Figure 16.1 | Claims and counterclaims. |
Figure 16.2 | Variation orders. |
Figure 16.3 | Suspension. |
Figure 16.4 | Procedure for claims. |
Figure 17.1 | Programme – time – delay – rate of progress. |
Figure 17.2 | An example of a network analysis. |
Figure 17.3 | Critical path diagram associated with the network analysis in Figure 17.2. |
Figure 18.1 | Certificates and payments. |
Figure 19.1 | Procedure under clause 67 of the Red Book. |
Figure 19.2 | Procedure under the provisions of the new alternative version of clause 67 contained in the 1996 Supplement. |
Figure 23.1 | Number of words in the FIDIC forms. |
Figure 23.2 | Number of sub-clauses in the 1999 Red Book. |
Figure 26.1 | Agenda for the first meeting and site visit, to be adjusted for other visits. |
Table 9.1 | Determination by the engineer in favour of the contractor. |
Table 9.2 | Determination by the engineer in favour of the employer. |
Table 9.3 | Determination by the employer against the contractor. |
Table 10.1 | The engineer’s proactive duties and authority. |
Table 10.2 | The engineer’s reactive duties and authority. |
Table 10.3 | The engineer’s passive duties. |
Table 12.1 | Notices required to be given by the employer to the contractor under the contract. |
Table 13.1 | The phases of a construction project in chronological order. |
Table 13.2 | Notices required to be given by the contractor under the contract. |
Table 23.1 | The Fourth Edition of the Red Book and the corresponding conditions in the 1999 Red Book. |
Table 23.2 | The 1999 Red Book and the corresponding conditions in the Fourth Edition of the Red Book. |
Table 23.3 | Cost, with or without profit. |
Table 23.4 | Sub-clauses relating to extension of time. |
The Author
Dr Bunni is a chartered engineer, conciliator/mediator and registered chartered arbitrator. He is Past President of the Association of Consulting Engineers of Ireland and Past President of the Chartered Institute of Arbitrators and Past Chairman of its Irish Branch. He received his MSc from Manchester University and his PhD from London University. He has extensive experience in civil and structural engineering design, supervision of construction, contract management, construction insurance, arbitration and other methods of dispute resolution. He has acted as an expert witness, dispute board member, conciliator/mediator or arbitrator in hundreds of domestic and international disputes (as a sole arbitrator, member or chairman of a tribunal in over 105 cases of dispute with values in excess of £1m, involving parties from over 45 different jurisdictions).
Dr Bunni is a member of various technical committees in Ireland and abroad, including: the Dispute Resolution Panel of the Institution of Engineers of Ireland; the Board of Directors of the London Court of International Arbitration; the Commission on International Arbitration of the ICC, Paris; the Standing Committee of the ICC International Centre for Expertise, Paris; and the Board of Trustees of the Dubai International Arbitration Centre. Dr Bunni is a member of the Panel of Arbitrators of a number of Arbitral Institutions and Organisations. He is Past Chairman of FIDIC’s Standing Committee on Professional Liability; FIDIC’s Task Committee on Construction, Insurance and Law; and its follow-up committee.
Dr Bunni was appointed Visiting Professor at Trinity College Dublin in December 1996, a position he continues to hold, and in March 2000 he was elected a member of the International Council for Commercial Arbitration, ICCA, which is a gathering by co-option of the foremost leaders in the field of dispute resolution.
Besides this book, Dr Bunni is the author of a large number of technical papers and two books on construction insurance, the latest of which is now in its second edition under the title Risk & Insurance in Construction, published by Spon Press, London, in 2003.
Dr Bunni has lectured extensively and has been invited to speak in many countries in Europe, Asia, Africa, North and South America and in New Zealand. He has organised and lectured at courses on various topics relating to construction contracts for FIDIC, the World Bank, the Munich Reinsurance Company, the Institution of Engineers of Ireland, the Chartered Institute of Arbitrators and other organisations.
Dr Bunni has been awarded a number of awards for: innovation; structural design for work he has done; and in November 1995 he was awarded the Institution Prize by the Institution of Engineers of Ireland (its premier prize) for his work and series of lectures on its Conciliation Procedure. He was awarded this prestigious prize once again in March 2004 for his ‘contribution of outstanding merit … to the benefit of the members (of the Institution)’. Only very few have received this prize twice.
Preface
The Fourth Edition of the Red Book was published in 1987. It was first subjected to minor editorial amendments in 1988 and was later amended more significantly in 1992. The 1992 form was such a success that the World Bank adopted it in its Standard Bidding Documents in January 1995, albeit with some further mandatory amendments of its own. The most important of these mandatory requirements concerned the role of the engineer under clause 67 of the Red Book and the adoption by the Bank of the concept of a Dispute Review Board to replace the engineer in the process of dispute resolution. FIDIC responded in 1996 by introducing its Supplement to the Fourth Edition of the Red Book, which was published in November 1996. By that time, the Orange Book had already been published in 1995 as a standard form for design and build contracts. The second edition of this book, which was published in 1997, dealt with all these developments in contract forms.
Although the 1992 Fourth Edition of the Red Book with the 1996 Supplement formed an excellent combination in providing a standard form of contract that answered most of the criticisms at the time, and although its good and bad points were understood by its users, FIDIC decided in 1999 to replace it with a different form rather than introduce a fifth edition that could have simply tackled some of the issues that had developed in the meantime. The ‘new’ Red Book was intended to replace the 1992 Fourth Edition of the Red Book, with the ambition that the use of the Fourth Edition would cease with time and that new projects that were being contemplated at that time should immediately utilise the 1999 forms of contract. However, this ambition did not materialise as there appeared to be significant reservation on the part of users to adopt a form that was untested and untried within the industry. It is also unlikely to happen to any large extent in the future, for many reasons.
The main reason is perhaps that users are by now very familiar and comfortable with the provisions of the Fourth Edition of the Red Book, and particularly their version of it if they have changed the standard form to suit their own particular needs.
Furthermore, after 40 years of use, the meaning of most of the provisions of the Fourth Edition of the Red Book has become known through court decisions and some arbitral awards. Users were and are reluctant to start the process of adopting a new form of conditions of contract as they believe, maybe rightly so, that it is likely to cause further disputes and problems in an industry that is already overloaded with conflict.
The 1999 Red Book was accompanied by a new Yellow Book to replace the Orange Book, and a totally new Silver Book where most of the risks were allocated to the contractor. However, despite that spectrum of colour, the Fourth Edition of the Red Book stood the test of time and remained as a major source for conditions of contract for civil engineering projects worldwide, and particularly in certain regions of the world, such as the Middle East.
Hence, it became necessary for a third edition of this book to be published encapsulating these developments, but leaving the text of the Fourth Edition of the Red Book as the main feature and reference point. This decision was taken mainly because of the continued use and popularity of the Fourth Edition and because of the fact that the 1999 Red Book has retained most of the principles and many of the concepts of the Fourth Edition of the Red Book. However, despite retaining the 1992 Red Book as the main feature of this book, each of the 1999 forms has been allocated a separate chapter, with the anticipation that many of the problems that exist in these forms would demand Second Editions in the very near future for which more detailed commentaries would be appropriate.
The third edition of this book also takes into account the constructive comments that were received from reviewers and the changes and events that have taken place since 1997, for example: the changes which have taken place in the statutes and bye-laws of FIDIC and its Code of Ethics; the latest edition of the ICC Arbitration Rules, published in 1998; developments in claim and dispute procedures; the ADR Rules of the ICC; and developments in Dispute Boards and the very recent ICC Rules relating to them.
Chapters 7 ‘Sharing of Risks’ and 14 ‘Risks, Liabilities, Indemnities and Insurances’ were reconsidered in view of the Australian and New Zealand Standards relating to the topic of risk and risk management. Chapters 16 and 17 on claims and counterclaims were enlarged to consider new developments on the topic of delay and extension of time and to take into account the recent experiences in that field, including some of the new publications.
Chapter 19 ‘Dispute Settlement by Arbitration’ was extended to incorporate various aspects of the topic of arbitration and material relevant to clause 67 of the Fourth Edition of the Red Book, including some problems encountered in arbitration as a method of dispute resolution; and finally some recommendations towards a more cost effective and speedy arbitration procedure.
A new part has been added to the book. Part V comprises five new chapters: Chapter 22 provides an overview of the 1999 FIDIC forms of contract; Chapter 23 deals with the 1999 Red Book; Chapter 24 deals with the 1999 Yellow Book; Chapter 25 deals with the 1999 Silver Book; and Chapter 26 provides a comprehensive description of Dispute Boards: their advantages and disadvantages; types; the procedures that should be followed; a typical agenda; and experiences of their use.
Part VI replaces the chapter in the previous edition that provided the alterations, omissions and additions made in producing the Fourth Edition, and in this edition of the book gives a comparative analysis of the text of the 1999 three main forms of contract. This analysis was carried out by denoting the differences that exist between the three forms using the Red Book as the reference text.
Finally, I have deviated from the convention of using ‘he or she’ and adopted the use of the masculine pronoun; this should be taken to refer to both male and female.
Nael G. Bunni
January 2005
I am indebted to the Fédération International Des Ingénieurs-Conseils (FIDIC) for the permission granted to me to quote and reproduce some material from the various FIDIC forms of contract published by FIDIC from 1992 to date. These publications are the copyright of FIDIC and can be purchased directly from FIDIC’s offices at PO Box 311, CH-1215 Geneva 15, Switzerland, or from any of FIDIC’s member associations in over 60 different countries around the world. My thanks are also due to FIDIC for permission to have this book available for purchase from their bookshop, at the above address and at www.fidic.org/bookshop
I would like to express my gratitude to those people who helped in producing this edition of the book. I am especially indebted to a number of my colleagues for their specialist commentary and input into certain passages of this edition of the book. Although not mentioned individually, they will recognise themselves.
I owe special gratitude to Mary Farrell, my secretary, for patiently word-processing the successive drafts of the new material in this edition. I also gratefully acknowledge the assistance of Ms Siobhan Fahey BA, BAI, LLB, CEng, MIEI, MCIArb, for reading and commenting on the manuscript for the new material in this edition, for her valued research that followed and her suggestions.
To my daughters Lara and Lydia, I owe a special tribute. To Lara, BSc, HDipAppSc, for her IT input. In particular, however, I gratefully acknowledge the help extended by my daughter Lydia, LLB, LLM, ACIArb, to whom I owe special gratitude for her valuable research, suggestions and secretarial assistance throughout the preparation of this edition of the book.
Finally, I wish to add a special word of thanks to Julia Burden of Blackwell Publishing for her continued encouragement, patience and support during the production of this edition of the book.
The Third Edition
To Anne
Without her own help, support and understanding
this third edition would not have been possible
In the commercial activities of today’s highly complex society, standard forms of contract have become an essential part of the day-to-day transactions of most agreements. The majority of standard forms have been developed by commercial organisations for the purpose of efficiency, to build on the experience gained from the repeated use of these forms, but most of all for the optimum protection of one or both parties’ interests. Standard forms of contract developed for construction activities, however, have mostly been drawn up by independent professional organisations, rather than by one or other of the parties to the contract, in order to establish or to consolidate a fair and just contract. Knowledge accumulated through experience and recurrent use over a long period of time has brought about revisions and modifications in construction standard forms with the aim either of achieving greater certainty in the intention of the wording or of providing a response to the needs of the parties and/or society. The use of a standard form in construction contracts where tendering is the conventional method of obtaining quotations has also ensured a common basis for the comparison and evaluation of tenders.
In Europe, and more particularly in the United Kingdom and in Ireland, such forms were produced as early as the nineteenth century. A standard form for building contracts was used under the aegis of the Royal Institute of British Architects some time towards the end of the nineteenth century. This led to what became known as the ‘RIBA Form’ which was published in successive editions between 1909 and 1957. It later developed into what became known as the JCT Form (Joint Contracts Tribunal) when the 1963 and the 1980 Editions were published. In Ireland, the RIBA Form was followed by the RIAI Articles of Agreement and Schedule of Conditions of Building Contract, issued by the Royal Institute of the Architects of Ireland.
In civil engineering contracts, various forms which were used by different employers prior to the Second World War were combined by the Institution of Civil Engineers and the Federation of Civil Engineering Contractors in the United Kingdom into an agreed standard document. This was published in December 1945, and the document was thereafter known as the General Conditions of Contract and Forms of Tender, Agreement and Bond for Use in Connection with Works of Civil Engineering Construction, in short the ICE Form. In January 1950 it was revised and issued with the added agreement of the Association of Consulting Engineers, London. Other revisions followed in March 1951 (Third Edition); in January 1955 (Fourth Edition which was later amended in 1969); in 1973 (Fifth Edition); and in 1991 (Sixth Edition). These revisions reflected some changes in the law and in the practice of civil engineering.
To the credit of those responsible for drafting the ICE Form, many professional institutions all over the world modelled their own conditions of contract on its text, making only minor amendments to accommodate differences in local matters of law and nomenclature. The ICE Form was, however, drawn up mainly for the domestic scene in the United Kingdom. The obvious need for a similar form in the international construction field prompted the Association of Consulting Engineers in the United Kingdom, jointly with the Export Group for the Construction Industries in the United Kingdom, and with the approval of the Institution of Civil Engineers, to prepare a document for use in other parts of the world. It was published in August 1956 and became commonly known as the Overseas (Civil) Conditions of Contract (the ACE Form). Although in text and format this latter Form differed only slightly from the ICE Form, there were some minor changes in forty clauses as well as a small number of major alterations.
The most important of the minor changes were as follows:
The major alterations were as follows:
‘any such operation of the forces of nature as reasonable foresight and ability on the part of the Contractor could not foresee or reasonably provide against’.
Whilst this shift in risk in respect of accidental damage to the works was implemented in clause 20, a similar shift in risk was not implemented in respect of financial loss resulting from suspension of work, under sub-clause 40(l)(b), due to weather conditions which are also a form of the forces of nature;
The ACE Form as published in 1956 included a standard Form of Tender, an Appendix and a standard Form of Agreement. It was published in a blue cover which helped to distinguish it from the ICE Form. It was, perhaps, the first standard form of international conditions of contract for civil engineering works. In concept and style, however, it remained faithful to the original domestic form.
The ACE Form had only been used for a short period of time when the Conditions of Contract (International) for Works of Civil Engineering Construction was published in August 1957. This was based on the ACE Form, described above, and was also published in two parts. Perhaps because of its long title, in a very short time it became popularly known as the ‘Red Book’ (its cover was printed in red). It was prepared by the Fédération Internationale des Ingénieurs Conseils (the International Federation of Consulting Engineers, FIDIC) and the Fédération Internationale du Bâtiment et des Travaux Publics (the International Federation of Building and Public Works, now known as the International European Construction Federation, FIEC).
FIDIC is the international Federation of duly elected associations of consulting engineers representing the profession in their respective countries. Membership in the Federation is restricted to one association for each country. To qualify for membership, an association must demonstrate that its statutes, bylaws and regulations ensure that its members comply with the ethics and professional code of practice of a consulting engineer as outlined and according to the principles endorsed by FIDIC.1.1 These principles have developed over the years and significant changes were recently introduced as explained later in Section 5.1 of this book.
In addition to some editing changes and a few minor revisions in clauses 1, 16, 31, 34, 40, 53, 60, 65 and 69(2), a number of important modifications were made to the ACE Form in the evolution of the first edition of the Red Book. These were:
‘If the Contract shall not contain any rates applicable to the extra or additional work then suitable prices shall be agreed upon between the Engineer and the Contractor. In the event of disagreement the Engineer shall fix such prices as shall in his opinion be reasonable and proper.’
The Second Edition of the Red Book was published in July 1969, when the document was approved and ratified by the International Federation of Asian and Western Pacific Contractors’ Associations. A supplementary section containing Conditions of Particular Application to Dredging and Reclamation Work was then added as Part III. The Second Edition, however, included no changes in the text. A reprint of the Second Edition in 1973 added the approval and ratification by the Associated General Contractors of America and the Inter-American Federation of the Construction Industry.
However, the publication of the controversial Fifth Edition of the ICE Form in June 1973 provided an impetus for a further revision of the Red Book. This Fifth Edition of the ICE Form provided the civil engineering industry in the United Kingdom with a document which included major departures from the practice followed in its Fourth Edition. Three main commentaries were published in July and November 1973, analysing the effect of these changes. Both Abrahamson and Akroyd criticised the style, language and lack of clarity of the document. Akroyd inquired as to ‘whether this new document forms a contractor’s charter to riches?’1.2 Duncan Wallace, in an article published in November 1973 (with the title ‘The Modest Revision which Became a Torrent of Change’) called the Fifth Edition of the ICE Form ‘a new and radically revised contract’.1.3
The Fifth Edition of the ICE Form obviously provided food for thought for those responsible for the Red Book, and so it was in March 1977 that the Third Edition of the Red Book was published, incorporating some significant changes. These changes, however, did not follow in all respects those made in the ICE Fifth Edition. In the preface to his book on the Fifth Edition of the ICE Form,1.4 Duncan Wallace wrote:
‘… it is apparent that they [the draftsmen of the Third Edition of the Red Book] evidently considered and studiously avoided, all the principal difficulties (and indeed innovations) in the Fifth Edition, as well as a number of the anomalies in the Fourth Edition (with the single exception of the difficult Maintenance Certificate provisions in Clause 62, which have been swept away, quite rightly, in the Fifth Edition, but which are retained unchanged in the 1977 FIDIC Contract).’
As well as editing and other minor changes, a full list of the revisions is given in a supplement to a book by Duncan Wallace, dealing with the Red Book.1.5 The most significant revisions made for the Third Edition of the Red Book were as follows: