Cover Page

Code of Practice for Project Management for Construction and Development

Fifth Edition






Wiley Logo

Wiley Logo

Foreword

The first edition of this Code of Practice, published in 1992, set out a job specification for a project manager and provided guidance on the project manager’s role. Since then project management has become an integral part of the construction industry and been responsible for its increased reliability and quality of product.

The next few decades experienced some significant changes within the industry with much focus towards changing our culture and communication. The interaction between the key participants in this industry, which produces many spectacular projects with increasing levels of complexity and technological prowess, continue to evolve around the necessity to deliver projects within an agreed budget, to a level of acceptable quality and within an agreed time scale.

The fourth edition, published in 2010, captured a range of themes across the industry. In this fifth edition, prepared in collaboration with a number of key professional bodies, the entire document has been overhauled to make it more contemporary while maintaining the integrity and rationale of the role of a project manager and project management in context of the construction industry.

Following the spectacularly successful delivery of the Olympics (London 2012) and continuing with the UK Crossrail project, construction is at the forefront of successful project management. This fifth edition, although developed specifically for the UK construction industry, will continue to satisfy the ever increasing demand for an authoritative document on this subject in other parts of the world.

I strongly commend this valuable multi-institutional code of practice to all the industry’s clients, to practising project managers and indeed to all students of the subject and their mentors.

Jack Pringle, PPRIBA Hon AIA FRSA DipArch BA (Hons)

Principal, Managing Director

Pringle Brandon Perkins+Will

Acknowledgements

The fifth edition of the Code of Practice, under the stewardship of David Woolven FCIOB, has strived to keep pace, and in places perhaps steer the directions ahead, in the construction industry which has been at the centre of economic regeneration and development across the globe.

In keeping with the fourth edition, the fifth edition has also been prepared by a broad representation of the industry, with contributions from built environment specialists and interdisciplinary cooperation between professionals within the built environment. I would like to take this opportunity to thank the many people who have helped with the fifth edition. A list of participants and the organisations represented is included in this book.

Specific note of thanks must go to Piotr Nowak, who has been ably and patiently assisted by Una Mair throughout the delivery process, for coordinating all the disparate elements of the review of the Code of Practice by maintaining the information flow and also for managing the digitalisation of all the figures and diagrams.

I would also like to thank Arnab Mukherjee, FCIOB, who led the editorial and drafting team, for the successful delivery of this document.

Chris Blythe

Chief Executive

Chartered Institute of Building

Working group for the revision of the Code of Practice for Project Management – Fifth Edition

Saleem Akram, BEng (Civil) MSc (CM) PE FIE MAPM FIoD EurBE FCIOB Director, Construction Innovation and Development, CIOB
Colin Bearne Gardiner & Theobald
Sarah Beck MRICS MAPM Royal Institute of British Architects
Andrew Boyle Tesco
Shaun Darley Voice of Reason Ltd/MB PLC
John Eynon Open Water Consulting
Dr Chung-Chin Kao Innovation & Research Manager, CIOB
Una Mair Scholarships & Faculties Officer, CIOB - Group’s Secretary
Gavin Maxwell-Hart BSc CEng FICE FIHT MCIArb FCIOB CIOB Trustee
Institution of Civil Engineers
Alan Midgley ARUP
Arnab Mukherjee BEng(Hons) MSc (CM) MBA MAPM FCIOB Technical Editor
Paul Nash MSc FCIOB Turner & Townsend
Piotr Nowak MSc Eng. Development Manager, CIOB
Dr Milan Radosavljevic UDIG MIZS-CEng ICIOB University of the West of Scotland
Eric Stokes MCIOB FHEA MRIN Salford University
David Woolven MSc FCIOB Chair Working Group
University College London
Roger Waterhouse MSc FRICS FCIOB FAPM College of Estate Management, Royal Institution of Chartered Surveyors, Association for Project Management

The following also contributed in development of the fifth edition of the Code of Practice for Project Management

Andrew Barr Davis Langdon
Richard Biggs MSc FCIOB MAPM MCMI Construction Industry Council
Richard Humphrey FCIOB FRSA FCMI FIoD MAPM PGCert FHEA EurBE Northumbria University at Newcastle
Vaughan Burnand Chair, Health & Safety Advisory Committee
Professor Farzad Khosrowshahi FCIOB Head of School of the Built Environment & Engineering Faculty of Arts, Environment & Technology, Leeds Metropolitan University
Dean Hyndman URS
Dr Sarah Peace BA (Hons) MSc Consultant, CIOB
Dr Aeli Roberts MSc GDL BVC ICIOB University College London
Dr Paul Sayer Publisher, Wiley-Blackwell, John Wiley & Sons Ltd, Oxford

List of tables

0.1 Definitions of project management

0.2 Specific key decisions

1.1 Duties of project manager

2.1 Contents for project brief

2.2 Client’s decision prompt list

3.1 Mapping common causes of project failure

3.2 Appointment of the project team consultants

4.1 Specimen agenda for pre-start meeting

4.2 Value engineering job plan

4.3 Result accelerators

4.4 Changes in the client’s brief: checklist

List of figures

0.1 Key project constraints

0.2 Project lifecycle

2.1 Outline project brief

2.2 Development of project brief from objectives

2.3 A summary of sustainable development

2.4 Site selection and acquisition

2.5 Relationship between scope for change and cost of change

2.6 Stakeholder mapping: the power/interest matrix

3.1 Stages of the project development

3.2 Typical project team structure

3.3 Elements of the strategy stage

3.4 Examples of (a) construction expenditure graph and (b) cash flow histogram

3.5 Tender procedure

4.1 Design team activities

4.2 Development of design proposals

4.3 Coordination of design work up to design freeze

4.4 Changes in the client’s brief

6.1 Small project installation testing and commissioning process and sign off

6.2 Large project installation testing and commissioning process and sign off

6.3 Project drawing issue flowchart

6.4 Services installation, testing and commissioning data sheets flowchart

6.5 Specialist maintenance contracts flowchart

7.1 Occupation: structure for implementation

7.2 Occupation: scope and objectives

7.3 Occupation: review and methodology

7.4 Occupation: organisation and control

List of diagrams – Briefing Notes

Scoring system for the Code for Sustainable Homes

Calculating the total points score

Site investigation activities

Stages of VM study

Mitigation action plan

Project risk assessment checklist

Project planning

Selecting a procurement route

Framework agreements

Call-off stage

Pre-tender process

Selection questionnaire

Pre-qualification interview agenda

Tendering process checklist

Tender document checklist

Mid-tender interview agenda

Returned tender review process

Returned tender bids record sheet

Post-tender interview agenda

Final tender evaluation report

Approval to place contract order

Final general checklist

Design development control sheet

Change order request form

Essential actions of project partnering

Generic risk transfer model in PPP/PFI projects

CIPS e-procurement lifecycle

DMTCQ – a framework for design management

0
Introduction

Project management

Project management has come a long way since its modern introduction to construction projects in the late 1950s. Now, it is an established discipline which executively manages the full development process, from the client’s idea to funding coordination and acquirement of planning and statutory controls approval, sustainability, design delivery, through to the selection and procurement of the project team, construction, commissioning, handover, review, to facilities management coordination.

This Code of Practice positions the project manager as the client’s representative, although the responsibilities may vary from project to project; consequently, project management may be defined as ‘the overall planning, co-ordination and control of a project from inception to completion aimed at meeting a client’s requirements in order to produce a functionally and financially viable project that will be completed safely, on time, within authorised cost and to the required quality standards’.

The fifth edition of this Code of Practice is the authoritative guide and reference to the principles and practice of project management in construction and development. It will be of value to clients, project management practices and educational establishments and students, and to the construction and development industries. Much of the information contained in the Code of Practice will also be relevant to project management practitioners operating in other commercial spheres.

Definitions

There are many definitions in existence for the term ‘Project Management’. The CIOB, in this Code of Practice, and in all other publications, uses the following definition:

Project management

The overall planning, coordination and control of a project from inception to completion aimed at meeting a client’s requirements in order to produce a functionally viable and sustainable project that will be completed safely, on time, within authorised cost and to the required quality standards.

Table 0.1 summarises a number of definitions of project management, as practiced by a selection of leading organisations involved in project management within the construction and building industry in UK.

Table 0.1 Definitions of project management

Organisation Definition of project management
Chartered Institute of Building The overall planning, coordination and control of a project from inception to completion aimed at meeting a client’s requirements in order to produce a functionally viable project that will be completed safely, on time, within authorised cost and to the required quality standards.
Association for Project Management The application of processes, methods, knowledge, skills and experience to achieve the project objectives. 1
British Standards 6079:2010 A unique set of coordinated activities, with definite starting and finishing points, undertaken by an individual or organisation to meet specific objectives within defined schedule, cost and performance parameters.
Office of Government Commerce (Department of Business, Innovation, and skills) The planning, monitoring and control of all aspects of the project and the motivation of all those involved in it to achieve the project objectives on time and to the specified cost, quality and performance.2
International Organization for Standardization 21500:2012 Project management is the application of methods, tools, techniques and competencies to a project. Project management includes the integration of the various phases of the project lifecycle.
International Project Management Association 3 IPMA Project management (PM) is the planning, organising, monitoring and controlling of all aspects of a project and the management and leadership of all involved to achieve the project objectives safely and within agreed criteria for time, cost, scope and performance/quality. It is the totality of coordination and leadership tasks, organisation, techniques and measures for a project. It is crucial to optimise the parameters of time, cost and risk with other requirements and to organise the project accordingly
Project Management Institute 4 PMI Project management is the application of knowledge, skills and techniques to execute projects effectively and efficiently. It is a strategic competency for organisations, enabling them to tie project results to business goals – and thus, better compete in their markets.

1 Definition as available at http://www.apm.org.uk/content/project-management (accessed November 2012).

2 Definition obtained from OGC Glossary of Terms & Definitions v06 March 2008 – at the time of publication the document is available at www.gov.uk through publications of the Department of Business, Innovation & Skills.

3 Definition obtained from ICB 3.0 – page 127.

4 Definition as available at http://www.pmi.org/About-Us/About-Us-What-is-Project-Management.aspx (accessed February 2013).

Characteristics of construction projects

Construction projects have inherent features that make them highly complicated enterprises. These features are characterised by high levels of complexity, uncertainty and uniqueness and include

Further pressures are created by a client needing to commit to key criteria such as the project duration and cost budget at an early stage, often before the full implications of what the project actually is about and how it is to be implemented have been developed in detail.

Most participants to the project are involved because they are offering a service or product as part of their business activity. It is usual practice for this involvement to be a formal contractual agreement with an agreed fixed, lump sum price based on a definition of the service or product required. Throughout their contribution to the project, participants are therefore balancing protecting their commercial position with working towards helping to achieve the overall project objectives. This relationship is not without difficulties and does not always work to the best advantage of the client or the project.

Characteristics of construction project management

Construction projects are intricate, resource consuming and often complex activities. The development and delivery of a project typically consists of several phases, sometimes over lapped but always linked, requiring a wide variety of skills and specialised services to balance the key project constraints (Figure 0.1). In progressing from initial feasibility to completion and occupation, a typical construction project passes through successive somewhat distinct stages that necessitate input from such asynchronous areas such as financial institutions, regulatory and statutory organisations, members of the public, engineers, planners, architects, specialist designers, cost engineers, building surveyors, lawyers, insurance companies, constructors, suppliers, tradesmen and cost managers.

During the construction stage itself, a project of relatively simple design and methodology involves a wide range of skills, materials and a plethora of different but often sequential activities and tasks that must follow a predetermined order that constitutes a complicated and sensitive pattern of individual criteria and restrictive sequential relationships.

The Construction Industry Council (CIC) suggests that the primary purpose of project management is to add significant and specific value to the process of delivering construction projects. 1 This is achieved by the systematic application of a set of generic project-orientated management principles throughout the life of a project. Some of these techniques have been tailored to the sector requirements unique to the construction industry.

The function of project management is applicable to all projects. However, on smaller or less complex projects, the role may well be combined with another discipline, for example, leader of the design team. The value added to the project by project management is unique: no other process or method can add similar value, either qualitatively or quantitatively.

c0-fig-0001

Figure 0.1 Key project constraints.

Adding value

The raising of standards should lead significantly to the adding of value. Greater awareness can result in better design, improved methods and processes, new material choices, less waste, decreases in transportation costs and ultimately more efficient buildings, all of which can bring added value to the whole development process.

Scope of project management

Construction and development projects involve the coordinated actions of many different professionals and specialists to achieve defined objectives. The task of project management is to bring the professionals and specialists into the project team at the right time to enable them to make their best possible contribution, efficiently.

Professionals and specialists bring knowledge and experience that contributes to decisions, which are embodied in the project information. The different bodies of knowledge and experience all have the potential to make important contributions to decisions at every stage of projects. In construction and development projects, there are far too many professionals and specialists involved for it to be practical to bring them all together at every stage. This creates a dilemma because ignoring key bodies of knowledge and experience at any stage may lead to major problems and additional costs for everyone.

The practical way to resolve this dilemma is to carefully structure the way the professionals and specialists bring their knowledge and experience into the project team. The most effective general structure is formed by the eight project stages used in this Code of Practice’s description of project management.

Project lifecycle

The different stages of the project lifecycle as identified across the industry have been summarised and compared in Figure 0.2.

c0-fig-0002

Figure 0.2 Project lifecycle.

In many projects, there will be a body of knowledge and experience in the client organisation which has to be tapped into at the right time and combined with the professional and specialists’ expertise.

Each stage in the project process is dominated by the broad body of knowledge and experience that is reflected in the stage name. As described earlier, essential features of that knowledge and experience need to be taken into account in earlier stages if the best overall outcome should be achieved. The way the professionals and specialists who own that knowledge and experience are brought into the project team at these earlier stages is one issue that needs to be decided during the strategy stage.

The results of each stage influence later stages, and it may be necessary to involve the professionals and specialists who undertook earlier stages to explain or review their decisions. Again, the way the professionals and specialists are employed should be decided in principle during the strategy stage.

Each stage relates to specific key decisions (see Table 0.2) Consequently, many project teams hold a key decision meeting at the end of each stage to confirm that the necessary actions and decisions have been taken and the project can therefore begin the next stage. There is a virtue in producing a consolidated document at the end of each stage that is approved by the client before proceeding to the next stage. This acts as a reference mark as well as acting as a vehicle for widespread ownership of the steps that have been taken.

Table 0.2 Specific key decisions

Project stages Key high-level processes Key high-level objective Key high-level deliverables Key high-level resources (key driver)
Stage 1: Inception Project need ‘What is the need?’ Project initiation document (PID) Client team
Project manager selection (optional)
Project manager
Project mandate
Environmental mandate
Stage 2: Feasibility Project brief ‘Is the need feasible?’ Project brief Client team
Project manager selection Signing off business case Project manager
Feasibility studies Specialist consultants
Business case
Funding options
Delivery parameters
Stage 3: Strategy Project governance ‘How will the need be realised?’ Project execution plan Client team
Parameters Project manager
Project strategy Specialist consultants
Project organisation and control
Accountability and responsibility
Procurement strategy
Selection and appointment of project team
Tender procedure
Project execution plan
Stage 4: Pre-construction Design delivery process
Technical design and production information
Value management
Procurement of supply chain
Contractual arrangements
‘What do we need to build? How would it look like and function? How would we deliver it and manage it?’ Design outputs
Contractual arrangements
Client team
Project manager
Design team
CDM coordinator
Stage 5: Construction Performance monitoring and control
Health, safety and welfare systems
Quality management and control
‘Are we constructing what has been designed?’ Performance management plan Client team
Project manager
Design team
CDM coordinator
Constructor team
Stage 6: Testing and commissioning Commissioning services
Commissioning documentation
‘Is the building working as designed?’ Commissioning
documentation
Client team
Project manager
Design team
CDM coordinator
Constructor team
Commissioning team
Stage 7: Completion, hand over and operation Planning and scheduling handover
Handover procedures
Operational commissioning
Client occupation
‘How do we use the building?’ Handover documentation
Health and safety file
Client team
Project manager
Design team
CDM coordinator
Construction team
Commissioning team
Occupation and maintenance team
Stage 8: Postcompletion review and in use Post-occupancy evaluation
Project audit
Project feedback
Close-out report
Benefits realisation
‘Has the project satisfied the need?’ Project close-out report
Post-occupancy
Evaluation
Occupation strategy
Client team
Project manager
Occupation and maintenance
team

Having considered the social, economic and environmental issues, projects begin with the inception stage which starts with the business decisions by the client that suggest a new construction or development project may be required. Essentially, the inception stage consists of commissioning a project manager to undertake the next stage which is to test the feasibility of the project. The feasibility stage is a crucial stage in which all kinds of professionals and specialists may be required to bring many kinds of knowledge and experience into a broad ranging evaluation of feasibility. It establishes the broad objectives and an approach to sustainability for the project, and so exerts an influence throughout subsequent stages.

The next stage is the strategy stage which begins when the project manager is commissioned to lead the project team to undertake the project. This stage requires the project’s objectives, an overall strategy and procedures in place to manage the sustainability and environmental issues, and the selection of key team members to be considered in a highly interactive manner. It draws on many different bodies of knowledge and experience and is crucial in determining the success of the project. In addition to selecting an overall strategy and key team members to achieve the project’s objectives, it determines the overall procurement approach and sets up the control systems that guide the project through to the final post-completion review and project close-out report stage. In particular, the strategy stage establishes the objectives for the control systems. These deal with much more than quality, time and cost. They provide agreed means of controlling value from the client’s point of view, monitoring time and financial models that influence the project’s success, managing risk, making decisions, holding meetings, maintaining the project’s information systems and all the other control systems necessary for the project to be undertaken efficiently.

At the completion of the strategy stage, everything is in place for the pre-construction stage. This is when the design is developed and the principal decisions are made concerning time, quality and cost management. This stage also includes statutory approvals and consents, considering utility provisions such as water and electricity, monitoring of the environmental performance targets, and bringing manufacturers, contractors and their supply chains into the project team. Like the earlier stages, the pre-construction stage often requires many different professionals and specialists working in creative and highly interactive ways. It is therefore important that this stage is carefully managed using the control systems established during the strategy stage to provide everyone involved with relevant, timely and accurate feedback about their decisions. Completion of this stage provides all the information needed for construction to begin.

The construction stage is when the actual building or other facility that the client needs is produced. In modern practice, this is a rapid and efficient assembly process delivering high-quality facilities. It makes considerable demands on the control systems, especially those concerned with time and quality. The complex nature of modern buildings and other facilities and their unique interaction with a specific site means that problems will arise and have to be resolved rapidly. Information systems are tested to the full, design changes have to be managed, construction and fitting out teams have to be brought into the team and empowered to work efficiently. Costs and time have to be controlled within the parameters of project objectives and the product delivered to the quality and specification as set previously.

The construction stage leads seamlessly into a key stage in modern construction and development projects: the commissioning stage. The complexity and sophistication of modern engineering services makes it essential that time is set aside to test and fine-tune each system. Any environmental performance targets such as Building Research Establishment Environmental Assessment Method (BREEAM) certification can be used as a measure of the project’s performance. Therefore, these activities form a distinct and separate stage which should predominantly be complete before beginning the completion, handover and operation stage which is when the client takes over the practically completed building or other facility. In some instances, there may also be some post-occupation commissioning and testing.

The client’s occupational commissioning needs to be managed as carefully as all the other stages because it can have a decisive influence on the project’s overall success and environmental performance. New users always have much to learn about what a new building or other facility provides. They need training and help in making best use of their new building or other facility. It is good practice for their interests and concerns to be considered during the earlier stages and preparation for their move into the new facility at the right time so that there are no surprises when the client’s organisation takes occupation.

The final stage is the post-completion review and in-use stage. This provides the opportunity for the project team to consider how well the project’s objectives have been met and what lessons should be taken from the project. A formal report describing these matters provides a potentially important contribution to knowledge. For clients who have regular programmes of projects and for project teams that stay together over several projects, such reports provide directly relevant feedback. Even where this is not the case, everyone involved in a project team, including the client, is likely to learn from looking back at their joint performance in a careful objective review. Projects where a BIM protocol had been established, then information exchange between the delivery team and the operations team will form a key highlight of this stage. In some projects, the client may wish to extend the services of the project manager (and may be the BIM manager) to facilitate the transition from delivery to operation, including assessment of project benefits and updating the controls and procedures as necessary.

Notes